Alliant Raises Four-Year Investment Plan to $15.9 Billion
GenTek USA | November 4, 2026 | Industry News

Riverside Energy Center, January 2008. Existing plant, not the proposed upgrade. Cropped display: Dual Freq / Wikimedia Commons, CC BY-SA 3.0.
Alliant Energy has raised its planned capital spending to $15.9 billion for 2027–2030, a 19% increase from its previous four-year forecast. The utility announced the revision on October 29 as it outlined investments to serve growing electricity demand, including large data centers.
Alliant said its Iowa and Wisconsin utilities have contracted for 3.4 gigawatts of data-center demand and expect system peak demand to rise about 60% by 2031. Contracted demand is not the same as load already connected and operating.
The $15.9 billion is a company-wide investment plan, not a generation-only budget. It includes renewable energy and storage, thermal generation and liquefied natural gas infrastructure, electric and gas distribution, and other spending, according to Alliant’s earnings announcement.
Projects still face approval milestones
The company’s third-quarter Form 10-Q shows why the spending forecast should not be read as a list of completed facilities.
Wisconsin Power and Light applied in March 2026 for permission to install equipment intended to maintain and increase capacity and efficiency at Riverside Energy Center near Beloit, Wisconsin. Alliant expects a Wisconsin Public Service Commission decision in the second quarter of 2027.
In Iowa, Interstate Power and Light is seeking approval for approximately 720 megawatts of simple-cycle natural-gas generation in Linn County, with a decision expected in the first quarter of 2027. It also proposed the approximately 1,200-megawatt Riverhawk Energy Center near its existing Emery Generating Station, with a decision expected in the second quarter of 2027.
Those are the company’s expected regulatory timelines, not guaranteed approval or operating dates.
What this means for large power users
The practical distinction is between a utility’s long-term capacity plan and the date a particular customer can receive service. For facilities planning new loads in these territories, the useful questions are which generation, transmission and interconnection steps their service depends on, and which milestones remain unresolved. A capital budget alone does not establish a site’s energization date.